How does the Panama schedule work?

Four crews share two 12-hour shifts a day: a day shift and a night shift. On any date, one crew is on days, one crew is on nights and two crews are off. Every crew follows the same 14-day rhythm: 2 on, 2 off, 3 on, 2 off, 2 on, 3 off. That is 7 shifts in every 14 days.

A study by researchers at the US Naval Postgraduate School describes the Panama schedule this way: four teams covering two 12-hour shifts each day over a 28-day period, with each team working days or nights for 2 weeks before changing to the other shift. The crews start a week apart, so the four of them cover every day and every night.

Crew A, Panama preset, from Monday 4 January 2027
DayWeek 1Week 2Week 3Week 4
MondayDayOffNightOff
TuesdayDayOffNightOff
WednesdayOffDayOffNight
ThursdayOffDayOffNight
FridayDayOffNightOff
SaturdayDayOffNightOff
SundayDayOffNightOff

Panama schedule example: a 28-day grid

The grid shows Crew A in the shift pattern calendar's Panama preset, starting on Monday 4 January 2027. Crew A works day shifts on 4, 5, 8, 9, 10, 13 and 14 January, then night shifts on 18, 19, 22, 23, 24, 27 and 28 January. On Monday 1 February it is back on days and the 28-day cycle starts again.

The other three crews follow the same rhythm, started 7, 14 and 21 days later. Crew C works nights while Crew A works days, and the other way round. Crews B and D cover the dates when A and C are off. From this start date, Crew A has 182 shifts in 2027: 91 day shifts and 91 night shifts.

Read down the weeks to see the weekends. Crew A works Friday to Sunday in weeks 1 and 3 and has Friday to Sunday off in weeks 2 and 4. So each crew has every other weekend off. In week 4, the night shift that starts on Thursday evening ends on Friday morning, so that weekend starts a little later.

Panama vs Pitman: are they the same?

They share the same days on and off, and there is no single official definition of either name. Some scheduling guides treat Panama, Pitman and 2-2-3 as one pattern. Others keep Pitman for crews that stay on fixed days or fixed nights, and use Panama for crews that swap. Some use both names for the swapping version.

Employers write their own definitions. A 2017 agreement between the Town of Harrison, New Jersey and its police superior officers calls a Pitman schedule some combination of 14 twelve-hour days in a 28-day cycle: 168 hours a cycle and 2,190 hours a year. A 2024 written offer from Butte-Silver Bow, Montana to its police association sets 2,184 hours a calendar year on the Pitman schedule, with shift rotations lasting three to four months. So ask how often, if ever, your crews change between days and nights.

The RotationCal tools follow the same split. The Pitman calendar keeps crews on fixed shifts unless you turn on rotation. With rotation on, every crew swaps on the same date every 14 days. Crews A and C then match the Panama preset date for date. Crews B and D swap after a 2-day break instead of their 3-day break, so their shift types differ on some dates. For the four-crew Panama layout, use the Panama preset.

Hours, weekends and rest on a Panama shift pattern

Seven 12-hour shifts in 14 days is 84 hours, an average of 42 hours a week. Real weeks swing: with a Monday start, week 1 has 5 shifts (60 hours) and week 2 has 2 shifts (24 hours). Over a 365-day year the average is 2,190 hours. A dated year counts real shifts instead: from 4 January 2027, Crew A has 182 shifts, or 2,184 hours, before breaks, leave or overtime. Those are the same two figures that appear in the two agreements above.

In the UK, the Health and Safety Executive lists good practice for designing shifts. It suggests rotating shifts every 2 to 3 days or every 3 to 4 weeks, no more than 2 to 3 long or night shifts in a row, and 2 nights of full sleep when switching between day and night shifts. A Panama crew changes every 2 weeks, never works more than 3 shifts in a row, and changes only after its 3-day break. With shifts of 07:00 to 19:00 and 19:00 to 07:00, that leaves at least 3 free nights before each change. Use the list to ask questions about a rota, not to decide on its own that a rota is safe.

Make a Panama schedule calendar

Open the shift pattern calendar and choose the preset called Panama (14-day shift rotation). Enter the date your crew starts a block of day shifts, add four crews and set the year. If your next block is nights, follow Crew C, which starts on nights. Check the first 28 days against your real rota before you rely on it.

If your workplace calls its rota Pitman and crews stay on fixed days or nights, use the Pitman calendar instead. Then save the calendar on this device, print it or download it for your phone, and check the first month after you import it. Shift times, breaks and overtime rules come from your employer.

For general information only, not professional advice. Check the official sources below. Use your own judgement and speak to your employer or HR team before you act.

Common questions

Is the Panama schedule the same as 2-2-3?

The days on and off are the same: 2 on, 2 off, 3 on, then 2 off, 2 on, 3 off. Panama usually also means each crew swaps between day and night shifts every 14 days.

How many hours a week is a Panama schedule?

With 12-hour shifts it is 84 hours every 2 weeks, an average of 42 hours a week. Single weeks swing between 60 and 24 hours.

Do you get every other weekend off on a Panama schedule?

Yes. With a Monday start, each crew works Friday to Sunday one week and has it off the next. A night shift that starts on Thursday still ends on Friday morning.